TSSD IFFP 2022
2023 TM Amendment IFFP
TSSD IFA 2023
LS-1 Boat Harbor Pump Station
Project: LS-1 Boat Harbor Pump Station
Engineer: Bowen Collins
Contractor: Not yet awarded
Status: Under preliminary Design. Final Design to be completed by end of 2024 with Construction beginning in 2025. Will replace an existing 30 MGD Lift Station with a 83 MGD Pump Station.
CL-N2 66" Lakeside Interceptor
Project: CL-N2 66" Lakeside Interceptor
Engineer: Bowen Collins
Contractor: Not yet awarded
Status: Under preliminary Design. Final Design to be completed by end of 2024 with Construction beginning in 2025. Three (3) miles of 66" CCFRPM pipe from end of CL-N1 to new LS-1 Pump Station
CL-R1 Replace and Upsize Lehi/American Fork Outfall
Project: CL-R1 Replace and Upsize Lehi/American Fork Outfall
Engineer: Bowen Collins
Contractor: Not yet awarded
Status: Currently acquiring ROW. Anticipated Bid Summer 2023. Construction anticipated to be completed end of 2024. 2.3 miles of 54" CCFRPM Pipe.
CL-N1 66" Parallel Westside Interceptor
Project: CL-N1 66" Parallel Westside Interceptor
Engineer: Horrocks Engineers
Contractor: Sundt Construction
Status: Construction began mid-September 2022 & is anticipated to be completed Summer of 2024. Two (2) miles of 66" CCFRPM Pipe parallel to existing 54" RCP District Main.
If you have questions or concerns about the project please feel free to contact our public involvement team. Please see their contact information below:
- Hotline: 385-999-1929
- Email: info@TSSDWestsideInterceptor.com
- Website: www.TSSDWestsideInterceptor.com
EL-1 Generator Switchgear
Project: EL-1 Generator Switchgear
Engineer: Carollo Engineers
Contractor: COP Construction
Status: New Switchgear and Load Bank for Generator Building. Construction anticipated completion end of 2022.
TP-4 TP-5 East & West Side Clarifier Improvements
Project: TP-4 TP-5 East & West Side Clarifier Improvements
Engineer: Brown & Caldwell
Contractor: Not yet awarded
Status: Anticipated Bid Fall 2022 with construction complete end of 2023. Recoat Clarifiers, replace gates and actuators, update controls, modify RAS / WAS piping
Master Plan Package A Biosolids Disposal
Project: Master Plan Package A Biosolids Disposal
Engineer: Aqua Engineers / Brown & Caldwell
Contractor: Not yet awarded
Status: Preliminary Design of Thermal Dryer
Master Plan Package B South Area Improvements
Project: Master Plan Package B South Area Improvements
Engineer: Carollo Engineers / Brown & Caldwell
Contractor: Not yet awarded
Status: Preliminary Design of South Electrical Buidling, Tertiary Filtration, UV Building, Plant Outfall and Realign RMP 345kV power line.
Master Plan Package C PCAD Improvements
Project: Master Plan Package C PCAD Improvements
Engineer: Brown & Caldwell
Contractor: Not yet awarded
Status: Preliminary Design of Primary Treatment and Anaerobic Digestion
Master Plan Package D Utah Lake Shoreline & Wetlands Restoration
Engineer: Jacobs / Brown & Caldwell
Contractor: Not yet awarded
Status: Preliminary Desgin and Development of a Wetland Mitigation Plan
Capital Facilities Plan / Impact Fee Facilities Plan
Project: Capital Facilities Plan / Impact Fee Facilities Plan
Engineer: Bowen Collins
Contractor: None
Status: Plan to be complete by September 2022